For my weekly update, I wanted to let everyone know that I have conducted fieldwork for the application!
| Example of some of the Inspection Questions |
But I have successfully tested the application in the field! We have decided to use the Collector App in a connected setting (for now...might change later). It really is a fairly straightforward application to use, I have written up a tutorial on how to use the application for Pad Mount Transformer Inspections in both a connected environment and in a disconnected environment. To be sure that we wanted to use the Collector solely in a connected mode, I was sent out to the western parts of town where the cell phone service can be spotty. I had no trouble getting cell service for the IPad but I did have trouble finding Pad Mount Transformers as I had never been to that part of town before. I should have looked at my map before I went out to do fieldwork but I thought that I would just be able to find transformers on the roads that I was sent too...nope. The Pad Mount Transformers were all on side streets in housing developments....I didn't know that before going out. But I had fun exploring.
In total, I field tested about 30 Pad Mount Transformers. While I was out on my own testing the application, I was just visually inspecting the transformer from the outside. However, I was able to go out to the field with one of the inspectors and see first hand how the actual inspection would go. I was able to see inside both a single phase transformer (supplying houses) and a three phase transformer (supplying a business). It was nice to finally be able to see what I have been customizing the application for. The inspector told me that he'll take me into the substation at one point to see what that is like, should be cool!
| The green triangles represent the transformers that I field tested |
No comments:
Post a Comment